Case Studies

Proud to work with

Back to sectors
At Veolia we are always striving to deliver innovative ways to turn waste into a resource for our customers throughout the UK. Click below for some examples of our great work in action.

Kings College Hospital


The 949-bed King’s College Hospital is one of London’s largest and busiest teaching hospitals and provides a full range of local hospital services for over 700,000 people in the London boroughs of Lambeth and Southwark. It also plays a key role in the training and education of medical, nursing and dental students and is recognised nationally and internationally. The buildings include 46 wards, surgeries and theatres, clinics, dental institute, education centre and residences.

The challenge

Although the site has been under continuous development in response to changes in strategic planning and medical practices, only limited improvements had previously been made to the boiler house and utilities systems. The site was under pressure to reduce its energy consumption and, by association, its carbon footprint. With their heating boilers at the end of their operational life and not able to meet the future energy demands of the hospital, the Trust looked for ways of replacing them. The initial objectives were to replace the inefficient steam raising plant, reduce carbon emissions, create significant cost savings and redress structural problems with the existing subterranean boiler house.
 

The solution

To meet the site needs for heating, electricity and cooling Veolia* designed a CHP based energy solution that included standby generation. Following the award of the contract Veolia commenced operation of the existing boiler house, provision of temporary plant and the complex construction project to build and commission the new CHP based energy centre. This aspect of the project included demolition of the obsolete flue, strengthening of the existing boiler house and adding additional storeys to house the new plant. On completion of the new plant Veolia started management of the operation of the trigeneration CHP system that delivers electricity, heat, hot water, cooling and standby generation.

Cost savings of £450,000 per year

CO2 savings of 2,555 tonnes per year (25% of site emissions)

Major part in achieving the hospital's Carbon Management Plan


Key elements of the new energy solution:

  • 1.8MWe & 2.4MWe (total 4.2MWe) gas fired CHPs
  • new 5 core chimney
  • one 10 tonne/hour and two combination fired/exhaust gas waste heat boilers
  • two 1250kWe absorption chillers
  • one 1700k WInterface plate heat exchanger
  • two 2300 Kva standby diesel generators
  • new HV substation and LV Switchboard

 

Key technical achievements during the construction phase included:

  • construction of the plant on an area of site with very limited access without impacting patient environment
  • civil engineering taking into account subterranean workspace under access road
  • constructing additional storeys on top of the existing energy centre to house new boiler plant and chillers
  • maintaining utility supplies to the hospital throughout the construction phase
  • decommissioning of the former waste incinerator facility to house standby generators

 

The results

The design, installation, operation and maintenance of the energy centre by Veolia’s expert team resulted in better availability and control of utilities which delivers an improved patient care environment.

The replacement of the hospital’s 44 year old boilers went a long way to help meet the Trust’s target to reduce carbon emissions by 10 per cent in the first year (in line with the hospital’s Carbon Management Plan). The new plant had an 8% impact within the first 6 months of operation.

The energy solution also delivers cost savings of £450,000 per year (a decrease in the site’s energy costs of around 29%) and CO2 emission reductions of 2,555 tonnes per year (25% of the site CO2 emissions).